As part of an initiative to promote sustainability and energy efficiency, a solar power system was installed at the Heavy Equipment Plant in Awerij. The project included detailed design and comprehensive supply of materials, aiming to make solar energy a primary and efficient power source for the facility.
The scope of work included:
- Detailed design & sizing
- Procurement of all necessary materials and consumables
- 3240 solar panels divided by 180 strings, every 10 strings connected with one inverter string capacity (60) KW
- quantity of inverter (18) pcs
The station has a special control system that provides reports on daily, monthly, and annual production, gives fully reports about equipment capability and charts of production rate including time details and production level