RASEP entered into a contract with the Oil Pipeline Company (a subsidiary of the Iraqi Oil Ministry) for the engineering, procurement, construction and commissioning – on a turn-key basis – of:
- 70 MMSCFD gas compression unit (GCU) in Buzurgan oilfield
- 18” (70 km) sour gas pipeline connecting the GCU and GTU
- 220 MMSCFD gas treatment unit (GTU) in Halfaya oilfield for the sweetening, dehydration and dew point control of sour gas
The objective of the project is to gather and process the sour gas from Buzurgan and Halfaya
oilfields for the utilization in the power generation sector.
The project is fast-track with a challenging execution timeline of 15 months.